Following on from concerns raised at Kingswells Community Council and those raised separately by a number of local residents, Councillor Steve Delaney met this afternoon with representatives of Countesswells Development Ltd.
Steve said, “I was pleased to have had the opportunity to meet with the developers to discuss residents’ concerns about the closure of the Kingswells to Cults road and the disruption this will cause. It was a friendly but frank exchange of views and I’m pleased to now be in possession of much fuller information to share with residents”.
“We discussed timeframes for various stages of the works and I made it known that Kingswells residents were unhappy they had not been offered any information, given that the works are likely to impact more significantly on Kingswells than the small number of people living in the new Countesswells development”.
The Kingswells to Cults road will close for three months from 6 January 2020. This timeframe was confirmed as being inclusive of all works on the C128C as well as the enlargement works to the south side of the Kingswells roundabout. There will be no through access to the C128C from the roundabout during this time on safety grounds.
The second phase of the works, which will see the enlargement of the Kingswells roundabout on the north side, is to commence shortly after conclusion of phase one. These works are timetabled to take a further three months. During this time the A944 will remain open but there’s almost certainly going to be significant disruption on the section heading from Westhill towards Kingswells (north carriageway only).
Steve said, “I wa assured that works will go on for no longer than is absolutely necessary and the time of year, being winter, has already been factored into the timetable. Both the developer and the council have confirmed the works to the C128C cannot be carried out safely without closing the road”.
“Having now seen the plans, the significant works to the Kingswells to Cults road will be particularly welcomed by everyone who uses that route. I just struggle to understand why it needs to take three months to complete, given that there will be no traffic on the road during construction works”.
“The enlargement of the Kingswells roundabout will help increase capacity but my view is that may still struggle to handle traffic volumes at peak times even after the enlargement due to the fact there’s no plans to widen the lanes within the roundabout and these narrow lanes have been a cause for concern from the outset with HGVs having to straddle lanes due to their size”.